Construction progress II stage

1. Work on the casting floor ( screed ) on 23 floors in all sections.

2. Work on the construction of the transformer substation.

3. Work is underway on the device of heating.

4. Thermal insulation of the facade is made of 70%.

5. Work continues on the installation of gypsum cardboard boxes plumbing risers.

6. Work is underway on the device of niches electrical risers.

7. The electrical work is underway in the penthouses ( 24-25 floors).

8. Work is underway to dismantle the tower crane in section B.

9. Work is underway on the device of the stairs through the galleries.