Construction progress II stage

1. Work is underway to fill floors (screed) – up to 17 floors in all sections.

2. Window set to 100% (on all floors).

3. Fire alarm system installed in the basements of all sections.

4. to start work on the construction of the transformer substation.

5. Works on of heating device.

6. Insulation of facade – 50% complete.

7. From 3 to 15 floor-mounted plaster cardboard boxes plumbing risers.

8. Perform waterproofing of plumbing pipes.

9. Works on sanitation.